The Building Process with SJM Property Developments
Pre Build Preliminary Stage:
- An Estimate is given for the Proposed Build: 1 Week
- Draft Plans drawn up: 2 Weeks
- Council Planning Approval: 4 Weeks
- Soil Test & Report, BAL Assessment & Thermal Energy Rating completed: 2-3 weeks
- Final Drafting & Engineering Plans completed: 3 Weeks
- Building Surveyor (Certificate of Likely Compliance): 1 Week
- Council- Building Permit Approval: 3 Weeks
Total Preliminary timeframe: 16 Weeks Approx.
The Building Stage:
- SJM Property Developments Build Time: 12-20 Weeks
(Time will depend on the Site Condition & design of the Project)
- Occupancy & Final Inspection Certificates: 1-2 Weeks
House Build to Completion (Average): 15-18 Weeks
Move into your New Home

The Building Stages
Initial discussion Site Visit House Design Confirm Design Fixed Price quotation / Contract Building Design & Approvals House Construction Building Completion & Handover Warranty & Defects
Initial discussion
Site Visit
House Design
Confirm Design
Fixed Price quotation / Contract
Building Design & Approvals
House Construction
Building Completion & Handover
Warranty & Defects